Road Diversion Announced as Repairs on Atomic Bridge Starts

The work will take place in the next 20 days daily from 8:00 pm to 6:00 am except for Sundays when the section being worked on will be closed to traffic.

election2024

The Ministry of Roads and Highways has announced the commencement of repair works on the Atomic Bridge along the Accra-Madina Highway.

The work starts on Thursday, October 3, 2024, at 8:00 pm.

- Advertisement -

In a press statement, the Ministry said, “The Bridge Management Unit (BMU) of the Ghana Highway Authority will be working on the expansion joints, with 26 joints in total, 13 on each bridge.”

- Advertisement -

The work will take place in the next 20 days daily from 8:00 pm to 6:00 am except for Sundays when the section being worked on will be closed to traffic.

- Advertisement -

“The work will start on the Accra-bound bridge for the first 10 days and then move to the Madina-bound bridge for the remaining 10 days. Traffic will be diverted to the ground level of the bridge during this time.”

It comes after Ing. Aaron Nana Amponsah, Project Manager of the Bridge Management Unit and the sector Minister, Hon Francis Asenso-Boakye inspected the bridge.

Source:opemsuo.com

 

- Advertisement -

Get real time updates directly on you device, subscribe now.

- Advertisement -

- Advertisement -

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More