Ofankor-Nsawam road project: 100 Lawsuits impede works – Chief Engineer

Briefing the minister designate, Mr Bempong explained that the team had been able to complete a railway bridge, including an underpass at the Pokuase Interchange project, adding that the retaining wall was almost completed.

- Advertisement -

More than 100 lawsuits, ranging from human rights cases to ownership of portions of the road earmarked for the reconstruction of the 18.1 km Ofan­kor-Nsawam dual carriage­way project, are hindering the completion of work on schedule

With some of the cases dating back to 2022, the Chief Resident Engineer, Kwabena Bempong, told the Daily Graphic that his team would not be able to meet the government’s August deadline.

- Advertisement -

“These cases have dragged on for quite some time, and these are impeding the progress of the work because there are some areas where we have to relocate the utility lines like electricity, telephone infrastructure and water; and until they are moved, we are unable to complete the construction of our main roads and the service roads,” he said.

- Advertisement -

He added that work on the Nsawam Interchange had not begun due to the litigation and movement of the utilities.

That notwithstanding, the Chief Resident Engineer told the Minister designate for Roads and Highways, Francis Asenso-Boakye, when he paid a working visit to the site last week, that substantial progress had been made.

Briefing

Briefing the minister designate, Mr Bempong explained that the team had been able to complete a railway bridge, including an underpass at the Pokuase Interchange project, adding that the retaining wall was almost completed.

He said about 50 per cent of work had been done on 10 of the footbridges.

The Chief Resident Engineer added that work on the cross drain structures, also known as culverts, was 90 per cent complete.

See also  Fetish priest commits suicide after shooting girlfriend he accused of cheating

Work ongoing on the Ofankor-Nsawam road project

Work ongoing on the Ofankor-Nsawam road project

- Advertisement -

He said majority of the earth work and sub-base had also been laid from Pokuase.

At Amasaman, he said the team had done about 30 per cent of the three-tier interchange.

For Pobiman and Medie, about 77 per cent and 50 per cent work had been done on the interchanges, respectively.

He assured the minister that a substantial part of the road would be completed to ease the current congestion on the road.

However, Mr Asenso-Boakye charged the contractors to complete the work by October to ease traffic flow.

He said the project was dear to the government as it would not only ease the traffic but improve transportation between very important economic centres from Tema and Accra to Kumasi, and neighbouring countries.

The minister designate expressed satisfaction with work on the project so far.

They went further to the Accra-Kumasi road to assess and experience the level of deterioration on that stretch.

He bemoaned the maintenance culture of the public which had led to a further deterioration of the road.

 

Source:ghanaxpress

- Advertisement -

Get real time updates directly on you device, subscribe now.

- Advertisement -

- Advertisement -

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More